Upgrading Management with High Availability

In This Section:

Upgrading from R80 to R80.10

Upgrading from R77.xx to R80.10

Upgrading from R80 to R80.10

  1. Upgrade the primary management server to R80.10 using CPUSE.
  2. Do a clean R80.10 installation on the secondary management.

    Install the secondary Security Management Server the same way you installed the primary. For the primary, if you:

    • Did a clean install of R80
    • Added the R80 Jumbo Hotfix Accumulator
    • Upgraded to R80.10

    Repeat the same procedure for the secondary management server. If you do not install the secondary management server in the same way you installed the primary, the servers will fail to synchronize after SIC.

  3. Connect the secondary to the primary server.

    Note - You can reuse the same network object in SmartConsole.

  4. Initiate SIC between the primary and secondary management servers and wait for the two servers to synchronize.

Upgrading from R77.xx to R80.10

The Pre-Upgrade Verifier prevents the upgrade of a secondary management server in a Management High Availability deployment. To upgrade such a deployment you need to:

  1. Upgrade the primary management server using CPUSE
  2. Do a clean R80.10 installation on the secondary management
  3. Initiate SIC between the primary and secondary management servers and wait for the two servers to synchronize